WEST TEXAS GAS PIPELINE

Location:

Texas

Scope of Work

Spartan Engineering provided full service design and engineering to construct 208 miles of 30” pipe from Coyanosa, Texas to Mexico to transport approximately 500 MMSCF per day of natural gas to the Fermaca Pipeline in Mexico.
Spartan Engineering provided complete engineering design services, including Mainline Route Development,
HDD Design Drawings and Permit, Typical, Valve and Trap Construction drawings and construction drawings for five (5) Meter Stations. The Project Management team also provided Hydrostatic Testing Plans and Packages and coordinated Right- of- Way and Environmental Permitting. The Project Teams also provided Valve and Trap Fabrication Coordination, Material Coordination and Procurement Tracking. MOC Coordination for the project was provided by Spartan’s Project Management team. Spartan completed all project documentation with MTR Books, Weld Maps and Job Books.